Proposed construction of a boundary wall at Ruring’u stadium phase one.
Kshs 19,336,370.00
Nyeri County Government.
20 Months
The project’s client was the county government of Nyeri who saw the need to secure first the historic Ruring’u stadium by construction of a boundary wall before any other works is undertaken in the sporting complex.
We are happy to have been part of the project from inception to completion as the main contractors. The project involved constructor of the boundary wall gate and gatehouse for a period of 20 months.